Cross-Cultural Training Center Constuction Phases
(Based on $50/sq.ft.)
Phase One:
- student apartments #1 4000 ft. $200,000
- student apartments #2 4000 ft. $200,000
- staff house #2 (#1 exists)1500 ft. $75,000
- recreation area 800 ft. $40,000
- Phase one total:$515,000
Phase Two:
- kitchen 600 ft. $30,000
- dining 1000 ft. $50,000
- commons 1000 ft. $50,000
- staff house #3 1,500 ft. $75,000
- 3 classrooms 2000 ft. $100,000
- maintenance shop 5000 ft. $125,000 ($25/m.)
- Phase two total: $430,000
Phase Three:
- student apartments #3 4,000 ft. $200,000
- library/resource center 2,000 ft. $100,000 admin.
- offices 2,500 ft.$125,000
- staff house #4 1,500 ft. $75,000
- Phase three total: $500,000
Phase Four:
- chapel 1,500 ft. $75,000
- nursery/school 2,000 ft. $100,000
- staff house #5 1,500 ft. $75,000
- staff house # 6 1,500 ft. $75,000
- road paving 80,000 ft. $230,000
- Phase four total: $555,000
Total cost of Training Center: $2,000,000 U.S.
|
|